Skip to Main Content

Additional Nelson Mullins Alerts

Aerial View of the Atlanta Suburb of Marietta, Georgia

Jan. 23, 2026

Avoiding Unenforceable Penalties: Georgia’s Take on Liquidated Damages

By Jake Carroll, W. Carroll B. Hart

Liquidated damages clauses are a common feature in contracts across industries, including construction, where they serve as a mechanism to predefine compensation for contractual breaches, including delayed completion. However, under Georgia law, a poorly drafted liquidated damages clause may be invalidated as an unenforceable penalty, leaving parties without the intended protection. 

Understanding Georgia’s framework for enforceability is essential to drafting liquidated damages provisions that will withstand judicial scrutiny.

The Legal Standard for Enforceability in Georgia

Under Georgia law, liquidated damages clauses are enforceable if they satisfy three key criteria:

  1. Difficulty in Estimating Actual Damages: At the time of contract execution, the damage or injury caused by a breach must be difficult or impossible to estimate with precision.
  2. Intent to Provide Compensation, Not a Penalty: The parties must intend for the clause to compensate the non-breaching party rather than punish the breaching party. Courts will scrutinize evidence of punitive intent.
  3. Reasonable Estimate of Probable Loss: The stipulated amount must reasonably approximate the anticipated loss resulting from a breach. Georgia courts require a rational basis for the damages amount, focusing on compensation rather than deterrence. [1]

The party challenging the clause bears the burden of proving it constitutes an unenforceable penalty. In cases of ambiguity, Georgia courts lean toward preserving contractual freedom, provided the clause aligns with these principles.

Best Practices for Drafting Liquidated Damages Clauses for Georgia Construction Projects

  1. Conduct a Thorough Damage Analysis: Use project-specific data to estimate the potential losses resulting from delay or non-performance. For example, on a construction project, this might include lost rental income or additional financing costs.
  2. Avoid Ambiguity: Clearly state that actual damages are difficult to ascertain and that the clause is intended to provide a reasonable estimate of damages, not a penalty. Avoid using terms like “penalty” or “punishment” to describe the liquidated damages.
  3. Include a Savings Clause: Incorporate language explicitly stating that the liquidated damages are not intended to operate as a penalty and reflect the parties’ intent to compensate for actual losses.
  4. Tailor the Clause to the Contract: Ensure that the clause aligns with the specific project’s scope, timeline, and financial considerations. Overly generic provisions may fail to meet the reasonableness test.
  5. Document the Basis for the Clause: If possible, state the basis of the calculation in the liquidated damages clause and retain records of the analysis used to determine the damages rate or amount. This documentation can provide critical evidence of intent and reasonableness if the clause is later challenged. 

Examples of Challenges to Liquidated Damages Clauses in Georgia

In Georgia, courts have upheld liquidated damages clauses that demonstrate clear intent and a reasonable pre-estimate of potential losses. For instance, in City of Brookhaven v. Multiplex, LLC, the court scrutinized a $1,000 per day clause for delays in a construction contract and found it unenforceable because the amount was not based on a reasonable estimate of actual damages but rather intended to deter breaches. [2] By contrast, when a liquidated damages clause reflects actual anticipated losses and is supported by evidence of the parties’ rationale, Georgia courts are more likely to uphold it. [3]

Another illustrative case is Department of Transportation v. Fru-Con Construction Corp., where the contractor’s failure to provide timely notice of delays, as required by the contract, resulted in liquidated damages being assessed. [4] The court emphasized procedural compliance and the necessity of timely notice to preserve the validity of the damages clause.

To support enforceability, clauses should include language specifying that the liquidated damages represent an effort to pre-estimate potential losses, avoiding punitive implications. Proper documentation of the calculation methodology and clarity in drafting remain paramount for aligning with Georgia’s legal standards.

Liquidated damages clauses are a critical tool for managing contractual risk, particularly in construction projects where delays can have significant financial consequences. By adhering to Georgia’s legal standards and incorporating best practices, parties can create enforceable provisions that safeguard their interests and provide clarity in the event of a breach.

If you have questions about any of the matters discussed above, please contact one of the authors or your regular Nelson Mullins contact.

Jake Carroll advises clients in the construction, manufacturing, and real estate industries on commercial transactions, complex disputes, and risk management matters. Carroll is the co-author of the Georgia Construction Law Handbook, a leading treatise published annually, serves on the Board of Directors of the Atlanta Bar Association, and is an active member of the Atlanta Bar Association’s Construction Law Section, where he served as Chair from 2022 to 2023.

Carroll Hart is a Senior Associate in Nelson Mullins’ Atlanta office and focuses his practice on construction transactions and complex commercial and construction litigation. Hart has previously served on the board of the Construction Law Section of the Atlanta Bar Association.


 [1] City of Brookhaven v. Multiplex, LLC, 891 S.E.2d 60 (Ga. Ct. App. 2023).
 [2] City of Brookhaven v. Multiplex, LLC, 891 S.E.2d 60 (Ga. Ct. App. 2023).
 [3] Grayhawk Homes, Inc. v. Addison, 845 S.E.2d 356, 357 (Ga. Ct. App. 2020).
 [4] Department of Transportation v. Fru-Con Construction Corp., 426 S.E.2d 905 (Ga. Ct. App. 1992).